Basis of Justifiable Verification Costs
90% probability of compliance vs. 10% of not
Non-compliance will cost us $10mil
Cost risk = 10% of $10mil = $1mil
If we verify, we will reduce the loss to $1mil
If non-compliant
Cost risk = 10% of $1mil = $100k
So risk reduction = $900k
Any verification costing less than $900k that, with certainty, would detect non-compliance would add value.
If there is uncertainty of the verification activity discovering the non-compliance, say 50% probability, we would be justified in spending up to 50% of $900k; 10%: 10% of $900k, etc.
Testimonial
"The best was the depth and comprehensiveness of the many interrelated aspects of the subject matter – it’s applicability to real-world , large-size systems development"
Systems Engineering Course
delegate, Brazil
PPI currently presents courses on 6 continents

Featured Course
Systems Engineering Management
London, United Kingdom
27 February - 2 March, 2012
This 5-day course provides in-depth coverage of how to manage engineering projects to maximise project success, within the project’s given constraints. The course establishes principles and provides methods for successfully managing projects, and getting the best out of people, individually and in teams.
Training
Quicklinks
Systems Engineering NEWSLETTER
SyEN makes informative reading for the project professional, containing scores of news and other items summarizing developments in the field of systems engineering and in directly related fields.